Bridge Repair Works July-September

Published on Wednesday, 20 July 2022 at 3:50:23 PM

Tthe Shire's Operations team will be overseeing repair work to several bridges within the Shire over the next three months.

Traffic management will be in place on roads around each bridge and while full road closures are not expected, there may be some delays at each location while works are in progress.

We ask everyone to please drive carefully on the roads during this time and consider taking alternative routes where possible.

Details of each bridge are as follows:

    Lennard’s Brook Bridge - Cockram Road #0836
    Works duration: approximately 6 weeks
    Commencement date: 25/07/2022
    Expected completion date: 26/08/2022

    Nolans Bridge - Gingin Brook Road #4035
    Works duration: approximately 3 weeks

    Commencement date: 30/08/2022
    Expected completion date: 16/09/2022

      Junction Bridge – Gingin Brook Road #4036
      Works duration: approximately 1 week

      Commencement date: 19/09/2022
      Expected completion date: 23/09/2022

      Cowalla Bridge – Cowalla Road #4806
      Works duration: approximately 2 days
      Commencement date: 26/09/2022
      Expected completion date: 27/09/2022